Step by step
Load & feasibility check
Confirm your sanctioned load and connection type on the bill. Under NEPRA's distributed-generation regulations, system size is generally limited relative to your sanctioned load; NEPRA has revised these rules over time, so check the current limits.
System design
An engineer prepares the system design and single-line diagram (SLD) with inverter and protection details. The inverter must be on your DISCO's approved list.
Application to the DISCO
Submit the application with documents to your DISCO (e.g. LESCO, IESCO, FESCO, GEPCO). Many DISCOs now take applications online.
Technical review & site inspection
The DISCO reviews the file and inspects the installed system for compliance.
Approval / agreement
Once approved, an agreement is signed with the DISCO and, where needed, a NEPRA generation licence is processed.
Bidirectional meter installation
The DISCO installs a bidirectional (green) meter. After that, exported units are credited on your bill.
Documents you will need
These are the items we typically ask you to share so we can start a net-metering application. Your DISCO may ask for further papers.
- A recent electricity bill for the same connection
- A copy of the CNIC of the meter owner (the consumer named on the bill)
- Proof of ownership, or a tenancy / NOC document if the property is rented
- The sanctioned load shown on your bill
- Site photos (the roof or ground area, the existing meter, and the distribution board)
We prepare the technical file — the system design, single-line diagram, inverter documents and the DISCO application — as part of our installation work.
Timing
The DISCO sets the timing for review, inspection, the agreement and the bidirectional meter. A complete file with an approved inverter and a correct single-line diagram avoids most delays. We do not quote a fixed period, because that is not in our control.